Affordable Solar was a 28,745 square foot tenant improvement converting existing office space for new tenant multi use space to include new offices, training rooms, conference rooms, collaboration areas, research and development, business areas, break areas and updated restrooms. In addition, plumbing, mechanical and electrical systems updated.
The project GMP $2,895,000 and completed under budget with savings of $95,000.00 or 3.3% to the project which included end of project credit for Segregation, PNM Energy Rebates and un-used Owner Contingency and Allowances for final cost of $2,800,00.00.
The project had an aggressive schedule to meet clients’ needs for new facility and was completed in 5 months. The project was completed on time and within budgets.
Project was successful in part of preconstruction services which Enterprise Builders Corporation assisted in re-programming the project in conjunction with the design team as Affordable Solar had a change in space plan during construction. In addition to early works packages, Enterprise Builders Corporation was able to identify long lead times that would have impacted to the project and successfully substituted doors and frames, control systems, plumbing and light fixtures. These items were delivered and installed to meet the opening critical path date of March 30, 2023